Case study · 10 Jan 2026
Sewer rehabilitation
in a food plant.
Acidic cleaning agents had attacked the pipe invert. Rehabilitation was completed on the day after a public holiday – during ongoing operation.
Initial situation
When cleaners
attack the invert.
During self-monitoring at a meat cutting plant, a CCTV survey revealed three damaged DN 300 sewer sections. In each, the pipe invert was badly attacked – caused by the acidic cleaning agents used to meet high hygiene standards.
Rehabilitation was only possible within clearly defined maintenance windows. As the liner was not available for the first slot in February 2025, 2 May 2025 was chosen – the Friday after a public holiday. Work could not start until around 12 noon.
The project in figures
Key figures
of the project.
Reprofiling in preparation for the liner.
3 sewer sections
DN 300, two of 40 m and one of 20 m.
150 bar
High-pressure cleaning by jetting vehicle.
10 hours
From 12 noon to 22:00 on a single Friday.
No preliner
Less material, no microplastics.
Reprofiling
Invert repaired,
ready for lining.
The restored, sound invert made a preliner unnecessary. This saves material and also avoids microplastics.
Project data
Technology & setting.
Sewer rehabilitation during ongoing operation at a food company.
Process
From cleaning
to liner.
With no lateral connections in the invert area, work progressed quickly.
Conclusion
Right on time,
as planned.
Close coordination paid off: the client and the contractors were very satisfied, and the liner was installed as scheduled the next day.
Gallery
The process
in pictures.
ReproLining unit, mortar and reprofiling in the sewer. Click an image to enlarge it.