Case study · 10 Jan 2026

Sewer rehabilitation
in a food plant.

Acidic cleaning agents had attacked the pipe invert. Rehabilitation was completed on the day after a public holiday – during ongoing operation.

Sewer rehabilitation in a food plant
Eroded sewer invert with exposed reinforcement and pulling cable in place before reprofiling

Initial situation

When cleaners
attack the invert.

During self-monitoring at a meat cutting plant, a CCTV survey revealed three damaged DN 300 sewer sections. In each, the pipe invert was badly attacked – caused by the acidic cleaning agents used to meet high hygiene standards.

Rehabilitation was only possible within clearly defined maintenance windows. As the liner was not available for the first slot in February 2025, 2 May 2025 was chosen – the Friday after a public holiday. Work could not start until around 12 noon.

The project in figures

Key figures
of the project.

Reprofiling in preparation for the liner.

3 sewer sections

DN 300, two of 40 m and one of 20 m.

150 bar

High-pressure cleaning by jetting vehicle.

10 hours

From 12 noon to 22:00 on a single Friday.

No preliner

Less material, no microplastics.

Invert reprofiling with ReproLining® 0.5 and ERGELIT mortar in a non-man-entry sewer

Reprofiling

Invert repaired,
ready for lining.

The restored, sound invert made a preliner unnecessary. This saves material and also avoids microplastics.

Project data

Technology & setting.

Sewer rehabilitation during ongoing operation at a food company.

Site: meat cutting plant
Damage: pipe invert attacked by acidic cleaning agents
Scope: three DN 300 sewer sections, two of 40 m and one of 20 m
Cleaning: jetting vehicle at 150 bar
Process: ReproLining 0.5 with winch, steel cable and deflection pulley
Mortar: ERGELIT-KS 1, XWW3-certified
Quality: the mortar quantity placed emerges at the target manhole
Time window: Friday 2 May 2025 (after a public holiday), 12 noon to 22:00

Process

From cleaning
to liner.

With no lateral connections in the invert area, work progressed quickly.

Clean the sewer sections with the jetting vehicle at 150 bar
Place ERGELIT-KS 1 in front of the reprofiling unit in the start manhole
Pull the unit through the section in a controlled manner – the mortar fills the washouts
Install the liner the next day – without a preliner

Conclusion

Right on time,
as planned.

Close coordination paid off: the client and the contractors were very satisfied, and the liner was installed as scheduled the next day.

Gallery

The process
in pictures.

ReproLining unit, mortar and reprofiling in the sewer. Click an image to enlarge it.

Enquiry

Rehabilitation
during operation?

We work with you to plan the process, material and time window for your sewer rehabilitation.